Virginia Port Authority[Operator]{United States},United States Army Corps of Engineers[Sponsor]{United States}
项目状态:
Under construction
开始时间:
2010
结束时间:
2039
项目说明:
December 2019 - Construction underway on Phase I; May 2018 - Virginia's U.S. Senators seek USD1.5bn in non-federal investment to construct marine terminal; September 2017 - Office of Management and Budget approved request from U.S. Army Corps of Engineers for USD3mn in reprogrammed funds for Craney Island Eastward Expansion; June 2014 - Congress clears path for Craney Island Land Transfer; Construction began in 2010 for project; Initial funding for the project came in 2007; Project to be implemented in phases, phase I will complete by 2028 and phase II in 2039