Esperance Port Iron Ore Facility Project, Western Australia
国家和地区:
Australia
项目名称:
Esperance Port Iron Ore Facility Project, Western Australia
领域:
Port Expansion
项目类型:
Dry Bulk
项目性质:
Public
项目经费 (USD Millions):
112
规模:
9000
规模单位:
thousand tonne
参加单位:
Esperance Port Authority[Sponsor]{Australia},Asciano[Construction]{Australia},Marubeni Corporation[Sponsor]{Japan}
项目状态:
At planning stage
开始时间:
-
结束时间:
-
项目说明:
June 2016 - Negotiation with preferred proponent has ended due to lack of potential users and as a consequence of the low price of iron ore; May 2015 - Project gets delayed as biggest user Cliffs Natural Resources winds down production; June 2014 - McConnell Dowell withdrawn from the project; May 2014 - Yilgarn Esperance Solutions (YES) consortium named as preferred proponent to design, finance, build and operate project; Facility will increase capacity from 11mnt/yr to 20mnt/yr; Project cost - AUD120mn