Esperance Port Iron Ore Facility Project, Western Australia
国家和地区: Australia
项目名称: Esperance Port Iron Ore Facility Project, Western Australia
领域: Port Expansion
项目类型: Dry Bulk
项目性质: Public
项目经费 (USD Millions): 112
规模: 9000
规模单位: thousand tonne
参加单位: Esperance Port Authority[Sponsor]{Australia},Asciano[Construction]{Australia},Marubeni Corporation[Sponsor]{Japan}
项目状态: At planning stage
开始时间: -
结束时间: -
项目说明: June 2016 - Negotiation with preferred proponent has ended due to lack of potential users and as a consequence of the low price of iron ore; May 2015 - Project gets delayed as biggest user Cliffs Natural Resources winds down production; June 2014 - McConnell Dowell withdrawn from the project; May 2014 - Yilgarn Esperance Solutions (YES) consortium named as preferred proponent to design, finance, build and operate project; Facility will increase capacity from 11mnt/yr to 20mnt/yr; Project cost - AUD120mn