October 2021 - Construction underway; December 2020 - Qube has entered into an exclusive negotiation period with the LOGOS Property Group which remains subject to finalising outstanding commercial issues and approvals; April 2017 - Construction commenced; Project will include Import-export (IMEX) freight terminal with capacity for up to 1.05mn TEU per year and interstate freight terminal with capacity up to 500,000 TEU a year; Sydney Intermodal Terminal Alliance (SIMTA) will build and operate the project; Project cost - AUD1,825mn