Kentz Corporation Limited[Construction]{United Kingdom},Mitsui & Co.[Sponsor]{Japan},Portos e Caminhos de Ferro de Mocambique (CFM)[Sponsor]{Mozambique},Vale S.A[Sponsor]{Brazil}
项目状态:
Completed
开始时间:
2012
结束时间:
2017
项目说明:
May 2017 - Project inaugurated; July 2013 - Construction contract worth USD38mn awarded to Kentz; Construction commenced in July 2012; Project has a storage yard able to accommodate around 1mnt of coal, is expected to load about 150 ships/yr; Project is part of Nacala Integrated Logistic Corridor (CLN) with investment amounting to USD4.4bn