Paradip Port Trust[Sponsor]{India},JSW Group[Sponsor]{India}
项目状态:
Under construction
开始时间:
2019
结束时间:
2020
项目说明:
May 2020 - Construction underway and is scheduled to be completed in 2020; February 2019 - Foundation stone laid; April 2016 - JSW won mechanisation contract; October 2015 - CCEA approved project to be implemented on BOT basis; Project involves mechanization of East Quay berths-1, 2 and 3 at Paradip Port and increase their capacity from the existing 7.85 million tonnes to 30 million tonnes; Project cost - INR14.38bn