Bahia Mineracao (Bamin)[Sponsor]{Brazil},Bahia State Government[Sponsor]{Brazil},China Communications Construction Company (CCCC)[Sponsor]{China},China Railway Group[Sponsor]{China}
项目状态:
Under construction
开始时间:
2020
结束时间:
2026
项目说明:
November 2021 - Construction underway; September 2021 - Construction slated for completion in 2026; February 2021 - Porto Sul port complex will receive an additional BRL4.6bn (USD842.7mn) from Bamin; November 2020 - Construction commenced; August 2020 - Construction works set to commence on the project; January 2014 - Port Authority authorized the installation of the terminal; June 2013 - Bahia Mineracao was awarded contract to build and operate the project; Project is part of Porto Sul Port Complex, which was expected to have two terminal but later was reduced to one terminal; Project Cost - BRL22.5bn