A585 Windy Harbour - Skippool Dual Carriageway Project, North West
国家和地区:
United Kingdom
项目名称:
A585 Windy Harbour - Skippool Dual Carriageway Project, North West
领域:
Road
项目类型:
-
项目性质:
Public
项目经费 (USD Millions):
182
规模:
4.8
规模单位:
km
参加单位:
Highways England[Sponsor]{United Kingdom},Kier Group plc[Construction]{United Kingdom}
项目状态:
Under construction
开始时间:
2020
结束时间:
2023
项目说明:
October 2021 - Project due to be completed in 2023; May 2020 - Preparation works commenced; February 2020 - Kier Highways signed contract for the construction of the project; December 2018 - Planning inspectorate has agreed to examine Highway England's plans for the project; Project includes construction of a new dual carriageway between Windy Harbour and Skippool that will bypass the existing A585; Project cost - GBP150mn