项目说明: |
January 2021 - Project under planning stage; June 2020 - Contract awarded to Oman Gulf Company; February 2020 - Bids received for parts 3, 4 and 5; Project includes construction of 20 At-grade U-turns, service roads, 5 rest areas, 1 weigh station, 16 lay bays, 8 emergency median openings, 25 ROP parking, approx. 101 reinforced concrete box culverts for cross drainage and 110 pipe culverts for median10 pipe culverts for median drainage, median dykes and embankment protections; Project is part of 717.5 km Adam - Thumrait Road Dualisation Project |