Germany Federal Ministry of Transport and Digital infrastructure (BMVI)[Sponsor]{Germany}
项目状态:
At planning stage
开始时间:
2017
结束时间:
-
项目说明:
December 2021 - Phase II under planning stage; August 2021 - Phase I officially opened; September 2020 - Federal road 299 is set to be closed for 2 months to enable construction works; May 2020 - Phase-II is at planning stage; April 2020 - Construction underway on 440 meter long Auberg tunnel as part of Phase-I; Project comprise of 2 phases - Phase-I with 1.5 km and Phase-II with 6.3 km; Tunnel cost - EUR30mn (USD35mn)