项目说明: |
August 2021 - Rehabilitation works for the 59.9km Babadjou-Bamenda road project in Cameroon are likely to begin at the end of June, 2021 or early July, 2021; On January 14, 2021, it was stopped following an attack of armed secessionists from the North-West, Sogea Satom, the contractor for the construction project that started in 2017, notified of its withdrawal from the project justifying its decision by a case of force majeure caused by the security situation in the area; Project to be delivered in four sections, first section stretches from Babadjou to Matazem a distance of 17 km and it is around 38% complete owing to the work carried out by Sogea-Satom, second section which is about 18 km stretches from Matazem to Bamenda while Section 3 covers the 4.93 km bypass of the Bamenda cliff, 4th encompasses the school of champions - agency Amour Mezam Junction - finance Junction - vetinary junction -hospital roundabout - food market-city chemist roundabout and vetinary junction and has a total length of 11.99 km |