Rajasthan Public Works Department (PWD)[Sponsor]{India},SREI Infrastructure[Sponsor]{India},MBL Infrastructure[Sponsor]{India}
项目状态:
Under construction
开始时间:
2018
结束时间:
-
项目说明:
March 2021 - Some structure work is under process; September 2019 - Work stopped due to funds problem while 90% work has been completed as of February 2019 with some works remaining; May 2013 - Reached financial closure with public sector banks; PPP contract awarded to MBL and SREI consortium in January 2012; Project is being developed under Design-Build-Finance-Operate-Transfer (DBFOT); Project has a concession period of 16 years; Project cost - INR5bn