Queiroz Galvao[Construction]{Brazil},Paraguay Public Works and Communications Ministry (MOPC)[Sponsor]{Paraguay},Ocho A SA[Construction]{Paraguay}
项目状态:
Under construction
开始时间:
2019
结束时间:
2024
项目说明:
January 2022 - Project is already half-finished; October 2021 - Work already reaches 216.6 km, out of a total of 277 km of the project; August 2021 - Total completion reached 203.06 km with recent inauguration of 13.55km Section 8 of the corridor in Loma Plata; February 2019 - Construction commenced; March 2018 - Contract awarded to Corredor Vial Bioceanic consortium comprising Queiroz Galvao and Ocho ASA; Project forms part of Paraguay section of Bioceanic Corridor Road Project