Bishkek-Osh Road Upgrade, Phase-IV, Bishkek - Kara-Balta Section
国家和地区: Kyrgyzstan
项目名称: Bishkek-Osh Road Upgrade, Phase-IV, Bishkek - Kara-Balta Section
领域: Road
项目类型: Upgrade/Maintenance
项目性质: Public
项目经费 (USD Millions): 121
规模: 52
规模单位: km
参加单位: Eurasian Development Bank (EBD)[Financier]{Kazakhstan},China Railway No. 5 Engineering Group (CR5G)[Construction]{China},Ministry of Transport and Communications of Kyrgyzstan[Sponsor]{Kyrgyzstan},Asian Development Bank (ADB)[Financier]{Philippines}
项目状态: Under construction
开始时间: 2017
结束时间: 2021
项目说明: March 2021 - Construction 66% completed; November 2020 - Construction underway but due to coronavirus pandemic expected completion by 2021; May 2019 - Construction began in April 2017; March 2017 - Contract worth USD70mn awarded to China Railway No 5 Engineering Group; Project is being implemented under CAREC 3 Corridor Improvement Project; [B&R]
发布时间: 2017