国家和地区: |
Indonesia |
项目名称: |
Bogor Outer Ring Road Project, West Java |
领域: |
Road |
项目类型: |
- |
项目性质: |
Public |
项目经费 (USD Millions): |
196 |
规模: |
13.8 |
规模单位: |
km |
参加单位: |
Wiecon Co. Ltd[Consultant/Project Management]{Taiwan},PT Wijaya Karya[Sponsor]{Indonesia},PT Marga Sarana Jabar[Sponsor]{Indonesia},Indonesia Ministry of Public Works and Public Housing[Sponsor]{Indonesia},Wiecon Co. Ltd[Design/Architect]{Taiwan} |
项目状态: |
At planning stage |
开始时间: |
- |
结束时间: |
- |
项目说明: |
June 2021 - Section 3B is planned to be built in 2023; January 2021 - Section IIIA completed; April 2018 - Section IIB construction completed; March 2018 - Construction commenced on section III; January 2017 - Construction started on section IIB; April 2018 - Section IIB completed; May 2014 - Section IIA completed; Project to be carried out in 3 sections however section I, 3.85km (Sentul Selatan-Kedung Halang) was completed in 2009; Project cost - IDR2.7trn |