国家和地区: | Vietnam |
项目名称: | Cau Gie - Ninh Binh Expressway - Nam Dinh Province Expressway Project, Nam Dinh |
领域: | Road |
项目类型: | - |
项目性质: | Public |
项目经费 (USD Millions): | 230 |
规模: | 46 |
规模单位: | km |
参加单位: | Xuan Truong Construction Company[Construction]{Vietnam},Vietnam Ministry of Transport[Sponsor]{Vietnam} |
项目状态: | Under construction |
开始时间: | 2017 |
结束时间: | 2025 |
项目说明: | October 2021 - Construction underway; November 2020 - Cost has increased for both the phases; December 2017 - Groundbreaking ceremony held for phase I; Expressway will start at intersection with Cau Gie-Ninh Binh Expressway in Yen Bang Commune, Y Yen District, Nam Dinh Province and end in Nghia Phuc commune, Nghia Hung district, Nam Dinh province; Project to be carried out in 2 phases; Project cost - VND5.32trn |
发布时间: | 2017 |