国家和地区: | Chile |
项目名称: | Chacao Bridge Project, Chiloe |
领域: | Road |
项目类型: | Bridge |
项目性质: | Public |
项目经费 (USD Millions): | 740 |
规模: | 2.75 |
规模单位: | km |
参加单位: | OAS[Sponsor]{Brazil},Louis Berger Group[Consultant/Project Management]{United States},Bentley Systems[Consultant/Project Management]{United States},Arup Group[Consultant/Project Management]{United Kingdom},TESolution[Consultant/Project Management]{South Korea},Aas Jakobsen[Design/Architect]{Norway},Systra[Design/Architect]{France},Hyundai Engineering and Construction Co Ltd.[Construction]{South Korea},Chile Ministry of Public Works (MOP)[Operator]{Chile} |
项目状态: | Under construction |
开始时间: | 2018 |
结束时间: | - |
项目说明: | September 2021 - Work is 30% complete; October 2020 - The Ministry of Public Works and Hyundai signed the agreement that ends the dispute over cost overruns in the construction of the project; March 2018 - Construction commenced; 2.75km suspension bridge will connect the Chilean mainland with Chiloe Island |
发布时间: | 2018 |