January 2022 - Construction on first stage of project is expected to be completed in 2023; July 2021 - Work on the construction of viaducts has started; February 2021 - Design documentation is currently being updated; January 2021 - GDDKiA awarded construction contract worth PLN89.5mn (USD24mn) to Budimex SA; December 2020 - Project will be designed by DiM; July 2020 - GDDKiA sent a tender notice for project; December 2019 - GDDKiA has terminated contract with Energopol Szczecin; September 2019 - West Pomeranian Voivode issued a permit for implementation of project; March 2018 - Construction contract awarded to Energopol Szczecin; Tender was announced in October 2015; Environmental decision for project was taken in December 2012; Project will be divided into 2 sections, Section 1 from Hakena roundabout to intersection with the current DK13 (4.2 km) and Section 2 from Siadlo Gorny to the Szczecin West junction (2.3 km); Project cost - PLN184.6mn