Bank Gospodarstwa Krajowego[Financier]{Poland},Transprojekt Gdanski Sp. o.o[Consultant/Project Management]{Poland},GDDKiA[Sponsor]{Poland}
项目状态:
At planning stage
开始时间:
-
结束时间:
2023
项目说明:
January 2022 - Project under planning stage; September 2021 - Seven offers were submitted in the tender procedure; August 2021 - Tender has been announced for the program concept; July 2021 - Waiting for the environmental decision to be issued; April 2021 - Technical-Economic-Environmental Study (STES) documentation is ready for the project; January 2021 - 5th variant of bypass has been adopted for construction of bypass; December 2020 - Evaluation Committee approved the STES document for construction; Project is part of 100 ring roads construction program for 2020-2030; Project Value - PLN590mn