Malaysian Ministry of Works (Kementerian Kerja Raya)[Sponsor]{Malaysia}
项目状态:
Under construction
开始时间:
2018
结束时间:
2021
项目说明:
December 2019 - Tender for installation of electrical system on the road is underway; October 2018 - Construction underway on phase 2B, and project is expected to be completed by March 2021; Project is divided into 3 phases - MYR42.16mn (USD10mn) Phase 1 (upgrading existing 2 km road at Jalan Alor Mengkudu which has been completed in May 2014), MYR176.46mn (USD42.5mn) Phase 2A (building a new 3.8 km road from Jalan Alor Mengkudu to Jalan Datuk Kumbar which has been completed in July 2018) and MYR97.71mn (USD23.5mn) Phase 2B (build a 2.2 km new road from Jalan Datuk Kumbar to Jalan Tun Razak / Langgar Road); Project cost - MYR316.33mn