African Development Bank (AfDB)[Financier]{Cote d`Ivoire},China Wu Yi Co[Construction]{China},Government of Kenya[Sponsor]{Kenya}
项目状态:
Under construction
开始时间:
2018
结束时间:
2022
项目说明:
December 2021 - Project is nearing completion and is expected to be completed before 2022 election polls; March 2021 - Commission has paid over 80 per cent of the 987 affected persons; September 2020 - Project delayed due to land compensation disputes; Project was launched in August 2017 but actual construction started in March 2018; Project starts from Cheplaskei on Eldoret-Nakuru highway through Kapsaret trading centre to Maili Tisa along Eldoret-Webuye highway before re-joining Uganda road; Project cost - KES6bn; [B&R]