Eldoret Southern Bypass, Uasin Gishu
国家和地区: Kenya
项目名称: Eldoret Southern Bypass, Uasin Gishu
领域: Road
项目类型: -
项目性质: Public
项目经费 (USD Millions): 59
规模: 32
规模单位: km
参加单位: African Development Bank (AfDB)[Financier]{Cote d`Ivoire},China Wu Yi Co[Construction]{China},Government of Kenya[Sponsor]{Kenya}
项目状态: Under construction
开始时间: 2018
结束时间: 2022
项目说明: December 2021 - Project is nearing completion and is expected to be completed before 2022 election polls; March 2021 - Commission has paid over 80 per cent of the 987 affected persons; September 2020 - Project delayed due to land compensation disputes; Project was launched in August 2017 but actual construction started in March 2018; Project starts from Cheplaskei on Eldoret-Nakuru highway through Kapsaret trading centre to Maili Tisa along Eldoret-Webuye highway before re-joining Uganda road; Project cost - KES6bn; [B&R]
发布时间: 2018