国家和地区: |
Poland |
项目名称: |
Hrubieszowa Bypass (National Road 74), Lublin |
领域: |
Road |
项目类型: |
Upgrade/Maintenance |
项目性质: |
Public |
项目经费 (USD Millions): |
61 |
规模: |
9.3 |
规模单位: |
km |
参加单位: |
European Union[Financier]{Belgium},Budimex[Construction]{Poland},Cardo Sp. z o.o.[Construction]{Poland},Dromet Sp. z o.o.[Construction]{Poland},GDDKiA[Sponsor]{Poland},HAK Construction[Construction]{United States} |
项目状态: |
Completed |
开始时间: |
2011 |
结束时间: |
2015 |
项目说明: |
October 2015 - Road opened for traffic; Project was initially awarded to HAK Construction, Dromet and Cardo Mosty however it was terminated when construction was 60% completed after Dromet went bankrupt and failed to fulfill the obligations of the contract and the workwas re-schedule and re-tendered to Budimex; Project cost - PLN227mn |