Kiewit Corporation[Construction]{United States},Zachry Construction[Construction]{United States},Texas Department of Transportation (TxDOT)[Sponsor]{United States}
项目状态:
Completed
开始时间:
2018
结束时间:
2021
项目说明:
August 2021 - Project completed six months ahead of schedule; August 2018 - Construction commenced; Project includes reconstruction and widening of SH 121 to accommodate a new interchange at I-635 and new direct connectors at SH 26 and FM 2499; Project is a part of DFW Connector project; Total length - 3 mile