国家和地区: | Qatar |
项目名称: | Industrial Area Road, Doha |
领域: | Road |
项目类型: | - |
项目性质: | Public |
项目经费 (USD Millions): | 638 |
规模: | 12.5 |
规模单位: | km |
参加单位: | Al Jaber & Makhlouf W.L.L[Construction]{Qatar},Public Works Authority (Ashghal)[Sponsor]{Qatar},Parsons Corporation[Consultant/Project Management]{United States} |
项目状态: | Completed |
开始时间: | 2012 |
结束时间: | 2019 |
项目说明: | October 2019 - Project completed; June 2019 - Ashghal opened unidirectional tunnel; Project extends from East Street 33 Intersection - Bu Hamour Intersection; Project will include 12.5 km with 4 lanes in each direction, tunnel of 670m, known as barwa City access and 5 multi-level interchanges known as East Street 33 Intersection, Umm Al Seneem Intersection, Wadi Lubara Intersection, Messaimeer Intersection and Bu Hamour Intersection; Project cost - QAR2.333bn |
发布时间: | 2012 |