Luanda Coastal Road, Phase II (Praia do Bispo - Corimba), Luanda
国家和地区:
Angola
项目名称:
Luanda Coastal Road, Phase II (Praia do Bispo - Corimba), Luanda
领域:
Road
项目类型:
-
项目性质:
Public
项目经费 (USD Millions):
142
规模:
7.8
规模单位:
km
参加单位:
China Railway Construction Corporation (CRCC)[Construction]{China},Angola Ministry of Construction[Sponsor]{Angola}
项目状态:
Under construction
开始时间:
2018
结束时间:
2020
项目说明:
May 2019 - Construction underway; August 2018 - Construction commenced; Project also includes construction of a viaduct at the intersection of the southwest road with the Samba road and a pedestrian bridge; Construction was launched on August 20, 2018 with a duration of 18 months to complete the project; [B&R]