WBHO Infrastructure[Construction]{Australia},SRG Global[Construction]{Australia},Government of Western Australia[Sponsor]{Australia}
项目状态:
Completed
开始时间:
-
结束时间:
2018
项目说明:
February 2019 - Final works completed on the project; December 2018 - Road open to traffic, but some work is still due which will be completed by early 2019; December 2015 - Western Australian Government has committed AUD58.3mn (USD42mn) for Stage II project; Stage I completed in May 2015; Project was carried out in 2 stages, Stage I (1.8 km) and Stage II (5.2 km); Project cost - AUD47.6mn