National Highways & Infrastructure Development (NHIDCL)[Sponsor]{India},MANARANJAN BRAHMA ENTERPRISE PRIVATE LIMITED[Construction]{India}
项目状态:
Under construction
开始时间:
2020
结束时间:
2021
项目说明:
July 2021 - Project has been delayed due to covid restrictions; November 2020 - Physical progress of this section is 25.02%; October 2018 - Ministry of Road Transport and Highways has agreed for final survey for alignment as per National highway specifications; March 2018 - Ministry of Road Transport and Highways has approved project; Project includes construction of two lane road with paved shoulder from Km 20.000 to Km 40.000; Project cost - INR2.72bn