Pakistan National Highway Authority[Sponsor]{Pakistan}
项目状态:
At planning stage
开始时间:
-
结束时间:
-
项目说明:
August 2021 - Project under planning stage; May 2021 - Work on the project will be started this year; July 2020 - Design and commercial feasibility would be ready by March 30, 2021, and would be presented to the PPPA Board for approval by April 15 while bids would be called by mid-September 2021; Project includes the rehabilitation of existing roads and the addition of new carriageways; Project cost - PKR200bn