国家和地区: |
India |
项目名称: |
Nagpur City Outer Ring Road Four Laning Project, Maharashtra |
领域: |
Road |
项目类型: |
Upgrade/Maintenance |
项目性质: |
Public |
项目经费 (USD Millions): |
164 |
规模: |
61 |
规模单位: |
km |
参加单位: |
Mumbai District Central Co-operative Bank Ltd.[Financier]{India},India Infrastructure Finance Company Ltd (IIFCL)[Financier]{India},IDBI Bank[Financier]{India},National Highways Authority of India (NHAI)[Sponsor]{India},MEP Infrastructure Developers[Sponsor]{India} |
项目状态: |
Under construction |
开始时间: |
2017 |
结束时间: |
2021 |
项目说明: |
August 2021 - Project is getting delayed and only 7 km road has been completed for Package-II; October 2020 - Project is delayed by 6 months due to Covid-19; February 2020 - 52% and 43.5% work have been completed on Package I and Package II respectively; January 2017 - MEP Infrastructure Developers has received the letter of appointed date for the project; October 2016 - Financial closure achieved; December 2015 - NHAI invited request for proposal (RfP); Project is being developed in two packages, Package I (33km) and Package II (28km) |
发布时间: |
2017 |