Narok - Sekenani Gate Road Project, Kajiado
国家和地区: Kenya
项目名称: Narok - Sekenani Gate Road Project, Kajiado
领域: Road
项目类型: Upgrade/Maintenance
项目性质: Public
项目经费 (USD Millions): 30
规模: 86
规模单位: km
参加单位: China Wu Yi Co[Construction]{China},Kenya National Highways Authority[Sponsor]{Kenya}
项目状态: Completed
开始时间: 2016
结束时间: 2019
项目说明: May 2020 - Project has been completed in 2019; March 2019 - China Wu Yi has stopped construction works on project after complaining of financing hitch in last four months; Project cost - KES3bn; [B&R]