国家和地区: |
Mali |
项目名称: |
Niono - Tombouctou Road Project |
领域: |
Road |
项目类型: |
- |
项目性质: |
Public |
项目经费 (USD Millions): |
170 |
规模: |
565 |
规模单位: |
km |
参加单位: |
SOGEA-SATOM[Construction]{France},Mali Ministry of Equipment and Transport[Sponsor]{Mali},US Millennium Challenge Corporation (MCC)[Financier]{United States},African Development Bank (AfDB)[Financier]{Cote d`Ivoire},European Union[Financier]{Belgium} |
项目状态: |
At planning stage |
开始时间: |
2010 |
结束时间: |
- |
项目说明: |
February 2021 - The works that were to resume have not resumed yet; November 2019 - Construction work to be resumed on the project; European Union is providing XOF129bn (USD211mn) for the project; Project to be carried out in 4 lots, Niono - Goma Coura (50 km) that was completed in July 2017, Goma Coura - Lere (165 km), Lere - Niafunke (121 km) and Niafunke - Timbuktu and Goundam - Dire slip road (198 km); Project Value - XOF97.5bn |