国家和地区: | Chile |
项目名称: | Nudo Quilicura, Santiago |
领域: | Junction/Interchange |
项目类型: | Upgrade/Maintenance |
项目性质: | Public |
项目经费 (USD Millions): | 550 |
规模: | 5.8 |
规模单位: | km |
参加单位: | Chile Ministry of Public Works (MOP)[Sponsor]{Chile},Abertis[Sponsor]{Spain} |
项目状态: | At planning stage |
开始时间: | 2017 |
结束时间: | 2022 |
项目说明: | October 2021 - Construction of a double Tunnel under the Lo Ruiz hill would begin within the first half of 2022; November 2018 - Stage 2 of the initiative is in the engineering development stage; October 2017 - Construction commenced on Stage I; Project involves 3 stages, USD2.5mn Stage I will be completed by February 2019, USD263mn Stage II includes construction of 1.5 km double-track tunnel under Lo Ruiz hill and Stage III involves joining of all the works |
发布时间: | 2017 |