GDDKiA[Sponsor]{Poland},IVIA SA[Consultant/Project Management]{Poland},Mota-Engil[Construction]{Portugal},European Union[Financier]{Belgium},ECM Group Polska[Consultant/Project Management]{Poland}
项目状态:
Completed
开始时间:
2019
结束时间:
2021
项目说明:
July 2021 - Project opened to traffic; Construction contract was awarded to Mota-Engil in November 2017 while construction started in May 2019; Bypass is being constructed in two phases, first phase will be completed in 2021 while second is planned to be completed in 2022; Project is part of 120 km S17 expressway between Piaski and Hrebenne; Project Value - PLN365mn