PT Pembangunan Perumahan (Persero)[Sponsor]{Indonesia},PT Virama Karya[Consultant/Project Management]{Indonesia},PT Wijaya Karya[Sponsor]{Indonesia}
项目状态:
Under construction
开始时间:
2020
结束时间:
2024
项目说明:
September 2021 - Construction works 41.63% completed on section II while section I is still in the bidding process; January 2020 - Construction of Section II began and is targeted for completion at the end of 2021; December 2018 - Project is currently in the tender process; Project is divided into 2 sections, Section I of Semarang-Sayung (10.39 km) and Section II of Sayung-Demak (16.31 km); Project cost - IDR15.3trn