Serang - Panimbang Toll Road, Banten
国家和地区: Indonesia
项目名称: Serang - Panimbang Toll Road, Banten
领域: Road
项目类型: -
项目性质: Public
项目经费 (USD Millions): 366
规模: 83.67
规模单位: km
参加单位: PT Adhi Karya[Sponsor]{Indonesia},PT Wijaya Karya[Sponsor]{Indonesia},Government of Indonesia[Sponsor]{Indonesia},Indonesia Ministry of Public Works and Public Housing[Sponsor]{Indonesia},Sino Group[Sponsor]{Hong Kong}
项目状态: Under construction
开始时间: 2020
结束时间: 2023
项目说明: September 2021 - Construction progress currently reaches 96.63% on Section 1; November 2020 - PT Adhi Karya (Persero) signed new contract for Section III while construction of Section I reaches 84.18%; April 2020 - Construction temporarily suspended due to Covid-19; January 2020 - Project is targeted to be fully operational by 2022 from previously expected by the end of 2019; Project is divided into 3 sections, Serang-Rangkasbitung section (26.50 km), Rangkasbitung-Cileles section (24.17 km) and Cileles-Panimbang section (33 km); Project cost - IDR5.33trn
发布时间: 2020