国家和地区: | Mali |
项目名称: | Sevare - Gao - Bourem - Kidal Road Project |
领域: | Road |
项目类型: | Upgrade/Maintenance |
项目性质: | Public |
项目经费 (USD Millions): | 350 |
规模: | 844 |
规模单位: | km |
参加单位: | African Development Bank (AfDB)[Financier]{Cote d`Ivoire},Mali Ministry of Equipment and Transport[Sponsor]{Mali},Arab Bank for Economic Development in Africa (BADEA)[Financier]{Sudan},European Union[Financier]{Belgium},The OPEC Fund for International Development (OFID)[Financier]{United Arab Emirates} |
项目状态: | Under construction |
开始时间: | 2021 |
结束时间: | - |
项目说明: | March 2021 - Construction and asphalting works on Sevare - Gao section started; April 2020 - Tender launched for Bourem - Kidal (285.83 km) section; August 2019 - Malian Government signed protocol of partial financing for Bourem - Kidal section with European Union and African Development Bank; February 2017 - Project under planning stage; Project is part of agreement for peace and reconciliation; Project Value - XOF215bn |
发布时间: | 2021 |