项目说明: |
December 2021 - Project under planning stage; October 2021 - Sagunto agrees to file an appeal against the project; July 2020 - Project has not moved in to execution stage; January 2019 - EUR0.1mn (USD0.11mn) allocated under 2019 budget for the ring road project; July 2015 - Ministry of Public Works and Transport approved the informative study of the project; Project to be carried out in 3 sections, North Section (USD11.9 km, USD129mn), South Section (30.5 km, USD256mn) and A-3 Connection (14.9 km, USD112mn); Project cost - EUR449.8mn |