国家和地区: |
Brazil |
项目名称: |
Goiania North - South BRT, Goias |
领域: |
Bus Rapid/Mass Transit (BRT) |
项目类型: |
- |
项目性质: |
Public |
项目经费 (USD Millions): |
78 |
规模: |
22 |
规模单位: |
km |
参加单位: |
Isolux Corsan[Construction]{Spain},Government of Goias[Sponsor]{Brazil} |
项目状态: |
Under construction |
开始时间: |
2015 |
结束时间: |
2021 |
项目说明: |
February 2022 - Works on the project are at a slow pace and expected to stop in the next few days; April 2021 - Section II should be delivered in the second half of this year and section I at the beginning of 2022; March 2018 - Works of BRT have officially resumed; Project has been paralyzed in June 2017; June 2015 - Contract awarded to Isolux; Project is divided into two sections, Section 1 from Isidoria Terminal to Cruzeiro do Sul Terminal, in Aparecida de Goiania and Section 2 from Recanto do Bosque Terminal, in the North region of city; Project Cost - EUR70mn |
发布时间: |
2015 |