February 2022 - Project under planning stage; October 2021 - Government has redesigned the plans for the construction of a bus rapid transit (BRT) project in the city route; It will include three stretches - Avenida Alcantara Machado, the Radial Leste, and the section from Sao Mateus Terminal to the Municipal Market; New design includes significant changes, such as a 200m tunnel at the arrival of the Parque Dom Pedro II subway (compared with 650m in an earlier design), 12 stations (instead of 13) and a bike path along the central axis; Project Cost - BRL1bn |