Swietelsky[Construction]{Austria},European Investment Bank (EIB)[Financier]{Luxembourg},Asfinag[Sponsor]{Austria}
项目状态:
Completed
开始时间:
2018
结束时间:
2021
项目说明:
September 2021 - Austrian part of the drive is completed while construction is underway on Slovenian part which will take until the beginning of 2028 to be opened for traffic; August 2020 - Boring works on Karavanke tunnel finally launched in Slovenia; February 2020 - EIB has agreed to provide EUR90mn (USD98mn) loan for project; January 2020 - DARS and Cengiz Insaat signed contract for Slovenian side; Construction on Austrian side started in September 2018; Project cost - EUR320mn (USD375mn)