项目说明: |
November 2021 - Project under planning stage; December 2020 - MITMA is given one year to carry out road safety audits of the layout and construction of the project; February 2017 - Ministry of Public Works and Transport has provisionally approved the technical document of the project; Project to be carried out in 4 sections, Zamora - Ricobayo Section (17.2km, USD86mn), Ricobayo - Fonfria Section (20.2 km, USD96mn), Fonfria - Alcanices Section (17.8 km, USD85mn) and Alcanices - San Martin del Pedroso Section (16.6km, USD142mn) |