Spain Ministry of Transport Mobility and Urban Agenda[Sponsor]{Spain},Vidal Obras Y Servicios[Construction]{Spain},Copcisa[Construction]{Spain}
项目状态:
Under construction
开始时间:
2018
结束时间:
2022
项目说明:
December 2021 - Construction underway; October 2021 - Minister of Finance has allocated EUR15mn (USD17.3mn) from general state budgets for 2022; April 2021 - The administrative processing of the construction project of the modification of the works contract continues; December 2020 - Construction works has been stopped; September 2020 - Construction underway; August 2018 - Construction commenced; May 2018 - Vidal Obras y Servicios - Copcisa JV has won construction contract of project; Project is last section of the A-22 Huesca - Lleida; Project cost - EUR46.7mn