国家和地区: | Poland |
项目名称: | A1 Tuszyn - Czestochowa Motorway, Piotrkow Trybunalski - Kamiensk Section |
领域: | Highway/Motorway |
项目类型: | Upgrade/Maintenance |
项目性质: | Public |
项目经费 (USD Millions): | 220 |
规模: | 24.2 |
规模单位: | km |
参加单位: | GDDKiA[Sponsor]{Poland},Mirbud[Construction]{Poland},Drogowa Trasa Srednicowa (DTS SA)[Consultant/Project Management]{Poland},Trakt SP. Z OO[Consultant/Project Management]{Poland},INKO Consulting Sp. z o. o[Consultant/Project Management]{Poland},European Union[Financier]{Belgium},SENER[Consultant/Project Management]{Spain} |
项目状态: | Under construction |
开始时间: | 2019 |
结束时间: | 2022 |
项目说明: | January 2022 - Construction underway; December 2021 - Project will be put into service next year; October 2019 - Construction started in September 2019; April 2019 - Mirbud SA signed construction contract; Project is part of 81 km A1 Motorway between Tuszyn and Czestochowa; Project Value - PLN868mn |
发布时间: | 2019 |