Government of Nigeria[Sponsor]{Nigeria},Julius Berger[Construction]{Nigeria}
项目状态:
Under construction
开始时间:
2018
结束时间:
2023
项目说明:
December 2021 - Project is being financed with the Presidential Infrastructure Development Fund; March 2021 - PDP raised the alarm over the alleged padding of the cost for the reconstruction of the project; September 2020 - Construction underway; June 2018 - Federal government flags off reconstruction project; December 2017 - Nigeria's Federal Executive Council (FEC) awarded contract worth NGN155.7bn (USD429mn) contract to Julius Berger; Project would be executed simultaneously in 3 sections, 165 km Zuba junction - Kaduna Western Bypass section, 75 km Kawo Bridge Junction - Zaria section and 137 km Zaria - Kano section; Project cost - NGN797bn