Varaha Infra Ltd.[Construction]{India},Dilip Buildcon Ltd[Construction]{India},National Highways Authority of India (NHAI)[Sponsor]{India},Meinhardt Group[Consultant/Project Management]{Australia},Sadbhav Engineering[Construction]{India}
项目状态:
Under construction
开始时间:
2019
结束时间:
-
项目说明:
February 2021 - Construction work 97.5% completed on Package-I; December 2019 - Dilip Buildcon receives provisional completion certificate for 50.86 km section which required investment of INR4.577bn (USD64.15mn); August 2015 - NHAI awarded contract of 50.86 km to Dilip Buildcon Ltd, Varaha Infra Ltd who will jointly undertake the project while Sabhav Engineering Ltd will complete the remaining stretch; Project Cost - INR8.137bn