Brazil National Department of Transport Infrastructure (DNIT)[Sponsor]{Brazil}
项目状态:
At planning stage
开始时间:
2018
结束时间:
-
项目说明:
January 2022 - Project under planning stage; June 2021 - Public notice for concession of project released; April 2021 - Headquarters monitors the progress of the BR-262 concession and duplication project; August 2020 - Concession of BR-262 is scheduled for the 1st quarter of 2021 and the contract must be signed in the first semester; March 2020 - Part of the duplication of the BR-262 could come out this year; December 2019 - Minister guarantees to resume work on the project in 2020; May 2019 - Project suspended due to irregularities in work; May 2018 - Duplication on first stretch between km 49 and km 56 begins