Barton Highway Duplication, New South Wales
国家和地区: Australia
项目名称: Barton Highway Duplication, New South Wales
领域: Highway/Motorway
项目类型: Upgrade/Maintenance
项目性质: Public
项目经费 (USD Millions): 152
规模: 52
规模单位: km
参加单位: Government of Australia[Sponsor]{Australia},New South Wales State Government[Sponsor]{Australia},SMEC Holdings[Construction]{Australia},Seymour Whyte Constructions[Construction]{Australia}
项目状态: Under construction
开始时间: 2021
结束时间: 2023
项目说明: November 2021 - Construction underway; March 2021 - Construction commenced; September 2020 - Seymour Whyte and SMEC will partner with the Transport for NSW to design and build the first stage of the project; May 2020 - Project receives funding worth AUD150mn (USD97mn) from Federal Government; June 2017 - NSW Government has allocated AUD50mn (USD38mn) for the duplication of 52 km Barton highway; Construction is expected to begin later in 2020; Project cost - AUD200mn