Gammon India Ltd.[Sponsor]{India},National Highways Authority of India (NHAI)[Sponsor]{India}
项目状态:
In tender/Tender launched
开始时间:
2011
结束时间:
2022
项目说明:
June 2021 - Completion deadline shifted to 2022 due to delay caused by Covid-19 pandemic; April 2015 - NHAI invited bids for the project; March 2012 - Gammon Infrastructure received LOA; Project was approved in October 2011; Project will be implemented under National Highway Development Programme (NHDP) Phase IV-A and carried out in DBFOT basis with BOT (Toll) mode of delivery; Concession period of the project is 23 years; Work on project started in 2011 but was stalled mid-way; Project cost - INR8.60bn