项目说明: |
December 2021 - Construction underway; June 2020 - Project included in second wave of investment of government's plan for economic reactivation; January 2019 - Government of Colombia decided to cancel contract with El Condor and construction on a toll was stopped on account of order from Supreme Court requesting prior consultations with the community on works, while a new tender would now be opened for the project; November 2016 - ANI has approved financial closure for project; May 2015 - Contract awarded to Construcciones El Condor to design, upgrade, build, operate and maintain the project; Project includes 350km of highway which includes 233km for improvement work and 166.5km for maintenance work; Project cost - COP387bn |