PNC Infratech Limited[Operator]{India},National Highways Authority of India (NHAI)[Sponsor]{India}
项目状态:
Under construction
开始时间:
2019
结束时间:
2021
项目说明:
February 2021 - Construction underway; July 2019 - Construction on 38 km has been completed as of May 2019; March 2017 - PNC Infratech has been declared the lowest bidder; November 2016 - NHAI invited bids for the project on Hybrid annuity mode; Project will be carried out under NHDP Phase-V on DBFOT basis; Project cost - INR19.37bn