国家和地区: |
Australia |
项目名称: |
City Link - Tulla Widening Project, Tullamarine, Melbourne, Victoria |
领域: |
Highway/Motorway |
项目类型: |
Upgrade/Maintenance |
项目性质: |
Public |
项目经费 (USD Millions): |
1030 |
规模: |
24 |
规模单位: |
km |
参加单位: |
Lend Lease Group[Construction]{Australia},VicRoads[Construction]{Australia},Government of Australia[Sponsor]{Australia},CPB Contractors[Construction]{Australia},State Government of Victoria[Sponsor]{Australia},Transurban[Operator]{Australia} |
项目状态: |
Completed |
开始时间: |
2015 |
结束时间: |
2019 |
项目说明: |
April 2019 - Project completed; August 2018 - Stage II, English Street exit to be opened in August 2018; July 2018 - Construction completed on Stage I in November 2017; February 2016 - Lend Lease won contract for Stage II; Project will be delivered in 2 Stages, 16 km Stage I will connect Bulla Road and Power Street and 8 km will connect Bulla Road - Melbourne Airport; Project cost - AUD1.3bn |
发布时间: |
2015 |